The purpose of this newsletter is to provide information to neighbors regarding construction of The Mather, which is located at the corner of Davis and Hinman. If you have specific questions regarding construction, please do not hesitate to call Michael Carney, Director of Construction Management, at Mather LifeWays: (847) 492.7436 or e-mail mcarney@matherlifeways.com.

 

February 2009

Below are details regarding how construction continues to progress.

The Mather North Topped Off in November 2008
The Mather North’s concrete structure was topped off at the 11th floor in November, finalizing an important chapter in our development.


In February, construction of the building enclosure will continue as the metal-stud framing, sheathing, and weather barrier are completed. The mason will also continue the brick and cast stone on the south, east, and west elevations, and the installation of the Juliet balcony precast will be completed.

In addition, the installation of the windows on the tenth and eleventh floors will be finalized, and sliding-glass balcony doors will installed on floors four through six. Interior wall layout and metal-stud framing will continue through the seventh floor as drywall is started on the second floor. Mechanical rough will continue on floors three through eight, and installation of the roofing systems will begin on the eleventh floor.

We are working to ensure an efficient, timely process—one that maximizes safety and minimizes disruption for residents and neighbors. We will continue to provide frequent updates.


 

 

Get all the info at
(847) 492.7400

or
click the link below for directions.

 

 

Contact Us | Privacy Policy | Site Index

Please e-mail webmaster@matherlifeways.com with comments or questions about our website.
© Copyright 2009 Mather LifeWays® and Ways to Age WellSM