The purpose of this newsletter is to provide information to neighbors regarding construction of The Mather, which is located at the corner of Davis and Hinman. If you have specific questions regarding construction, please do not hesitate to call Michael Carney, Director of Construction Management, at Mather LifeWays: (847) 492.7436 or e-mail mcarney@matherlifeways.com.
February 2009Below are details regarding how construction continues to progress. The Mather North Topped Off in November 2008
In addition, the installation of the windows on the tenth and eleventh floors will be finalized, and sliding-glass balcony doors will installed on floors four through six. Interior wall layout and metal-stud framing will continue through the seventh floor as drywall is started on the second floor. Mechanical rough will continue on floors three through eight, and installation of the roofing systems will begin on the eleventh floor.
|